Salvador Norte Shopping Centre Innovative cooling system solution cuts energy consumption by 17% for Salvador’s newest shopping centre.

​​​​​​​​

 
Requirement
The Salvador Norte Shopping Centre in Salvador, Brazil covers a total area of 107,000 m2, and spreads over 4 levels creating space for 229 shops.

From the project outset, energy efficiency through the use of state-of-the-art cooling technology, and a total system solution, were defined as key requirements for this new shopping complex. Key features of the cooling system included the use of thermal energy, decoupling of cooling and dehumidification processes, and the local production of cooling energy to avoid energy loss during transportation. All features are aimed at achieving optimum energy efficiency.

Following successful cooperation on previous projects with both the developer and the cooling system designer, IMI Hydronic Engineering was involved right from the very beginning.​

Solution
In the early design phase IMI Hydronic Engineering supported the choice of design principles and cooling system technology, and was involved in hydronic calculations and component specification until project completion.​

The required key features were implemented in IMI Hydronic Engineering’ system solution using products such as the Compresso to ensure a well pressurised system, and the STAD valve to provide accurate hydronic balancing. They not only help to meet the energy efficiency targets, but also provide the building’s tenants with an accurate and controllable room temperature and offer visitors a comfortable shopping experience.

Salvador Norte Shopping Centre is the first building in Brazil to be awarded the “Procel Edifica”, Brazil’s classification scheme to evaluate energy efficiency in buildings, and it received an “A” rating!

Facts
Project type Shopping centres
Building Salvador Norte Shopping
Location Salvador, Bahia, Brazil
Consultant Interplan
Owner Grupo JCPM

IMI in Action

Smart Solutions for Social Distancing
23 June 2020
50th Earth Day
22 April 2020
Simple tips to improve the comfort of your home office
23 March 2020
Important update
17 March 2020
Revolutionary new actuator feature
10 January 2020
Optimizing a chilled-water hydronic system
31 October 2019
Maintenance for energy savings
20 August 2019
Exciting project won in Luxembourg
15 July 2019
Pressurisation solutions
28 May 2019
HVAC system check-up list
03 April 2019
New version of HyTools app
15 March 2019
ISH 2019
12 February 2019
TA-Slider
09 December 2018
Winter is coming - check your customers' HVAC systems
26 September 2018
Air and dirt can undermine system performance
14 June 2018
TA-STAD
13 June 2018
The IMI Eye issue 9 has arrived
05 October 2017
Simply Compresso
05 October 2017
TA-Slider campaign
20 February 2017
Zeparo G-Force
13 February 2017
Salvador Norte Shopping